A ticket comes back rejected. The client says the rates don’t match the work order. Your billing coordinator is on the phone, the invoice is three weeks old, and the field supervisor who filled out the original document is already on a different site. You’re not getting paid this week.
If that situation sounds familiar, you’re dealing with something that affects almost every contractor running time-and-materials work in oil and gas and construction.
This guide covers exactly what a LEM is, what goes on one, why they get rejected, and what companies that have solved this problem are doing differently.
What Does LEM Stand For?
LEM stands for Labour and Equipment Manifest. In the US you’ll also see it spelled Labor and Equipment Manifest, and some companies expand it as Labor, Equipment and Materials. All three mean the same document: the record of who worked, what equipment ran, and what materials were used on a job.
Think of a LEM as the evidence file for an invoice. Without it, you can’t bill. With a bad one, you’ll wish you hadn’t tried.
What Is a LEM in Construction and Oil & Gas?
In both industries, a LEM is how time-and-materials work gets paid. What changes is the job site.
In oil and gas and pipeline work, LEMs back almost every service invoice. Operators expect one per crew per day, signed by their site rep, with a PO number and cost codes before they approve the charges. Large operators like Suncor and CNRL often have their own formats.
In construction, LEMs cover the work that isn’t part of a fixed-price contract: time-and-materials jobs, extra work, and changes the client asks for mid-project. A signed LEM is the proof that the work happened and the client agreed to it. If the client changes the scope, document it as a change order so the LEM lines match what was approved.
The reason it exists is simple: clients won’t pay for work they can’t verify. A LEM gives them the line-by-line breakdown they need to approve charges. For contractors, it’s the paper trail that protects revenue. For clients, it’s the record that confirms what they agreed to pay for.
When a LEM is filled out correctly and approved on time, billing is fast and disputes are rare. When it’s not, everything slows down.
What Goes on a LEM?
A complete LEM has three sections: Labour, Equipment, and Material. Each one captures specific information. Missing fields in any section are the fastest route to a rejected ticket.
Labour
The labour section documents everyone who worked on the job and what they did. A properly completed labour section includes:
- Worker names (or employee IDs, depending on client requirements)
- Job title or classification (operator, labourer, supervisor, etc.)
- Hours worked, broken down by regular time, overtime, and double time where applicable
- Bill rates for each classification
- Start and end times, including any standby or call-out time
Some clients, particularly large operators like Suncor or CNRL, have their own formats for this section. If your crew is working on a major operator’s site, confirm what they require before the job starts.
Equipment
The equipment section covers every piece of machinery, vehicle, or tool that was on-site and billable. It should include:
- Equipment type and description (e.g., excavator, vacuum truck, light plant)
- Equipment ID or unit number
- Hours of operation, including standby hours if applicable
- Whether the equipment is owned or rented
- Bill rates for each piece of equipment
- Operator name if billable separately from the labour section
Standby time is one of the most commonly missed line items in equipment sections. If a piece of equipment is on-site but waiting, and the client agreed to pay standby rates, it needs to be on the LEM.
Material
The material section tracks everything consumed or used on the job that gets billed back to the client. This includes:
- Material description and specifications
- Quantities used
- Unit of measure (litres, metres, tonnes, etc.)
- Unit cost
- Whether the material is a passthrough cost or marked up
Not all materials are billed back to the client. Some are covered by the contractor’s scope. Make sure your field crews know the difference before they start listing items.
Sample LEM
Here’s a completed LEM for one crew on one day. The company, names and rates are examples only.
| LEM No. | LEM-2026-083-014 | Job No. | 2026-083 |
| Date | Nov 10, 2026 | Job Name | Pipeline tie-in |
| Client | Great Operator Ltd. | Location | Wainwright, AB |
| Client Rep | R. Patterson | Purchase Order No. | PO788290 |
| Cost Code | 4100 Civil |
Labor
| Employee | Trade | RT hrs | RT rate | OT hrs | OT rate | Total |
|---|---|---|---|---|---|---|
| J. Martin | Equipment Operator | 10 | $95.00 | 2 | $142.50 | $1,235.00 |
| R. Singh | Laborer | 10 | $68.00 | 2 | $102.00 | $884.00 |
| A. Chen | Safety Lead | 10 | $62.00 | 0 | $93.00 | $620.00 |
| Labor subtotal | $2,739.00 |
Equipment
| Unit No. | Description | Qty | Unit | Rate | Total |
|---|---|---|---|---|---|
| EX-214 | 30-ton excavator | 8 | hr | $185.00 | $1,480.00 |
| EX-214 | 30-ton excavator, standby | 2 | hr | $92.50 | $185.00 |
| PU-118 | 3/4-ton pickup | 1 | day | $150.00 | $150.00 |
| Equipment subtotal | $1,815.00 |
Material
| Description | Qty | Unit | Unit cost | Total |
|---|---|---|---|---|
| 3/4" crushed gravel | 12 | tonnes | $38.00 | $456.00 |
| Geotextile fabric | 50 | m² | $2.40 | $120.00 |
| Material subtotal | $576.00 |
LEM total: $5,130.00
| Supervisor signature | D. Stewart (signed on-site) |
| Client signature | R. Patterson (signed on-site) |
Why this LEM gets approved:
- The PO number and cost code are at the top, so the client can match it to the right budget.
- Every rate matches the agreed price book, including overtime at 1.5x.
- Standby time is its own line at the agreed standby rate, not buried in run hours.
- The client rep signed on-site, before the crew left.
Want a blank version to start from? Download our free field ticket template.
Is a LEM the Same as a Field Ticket?
This question comes up a lot. The short answer: every LEM is a field ticket, but not every field ticket is a LEM.
In oil and gas, particularly in western Canada, “LEM” is the more common term for a document that captures labour, equipment, and materials on a time-and-materials job. “Field ticket” is the broader term used across industries for any document that records work done in the field.
In construction, you’re more likely to hear “daily log,” “field ticket,” or “T&M ticket.” The underlying purpose is the same: document the work so you can bill for it.
The practical distinction matters most when you’re working across industries or with clients who use different terminology. When in doubt, ask your client what they call it and what format they want it in. Using the wrong template, even with the right information, is enough to delay an approval.
Why Do LEMs Get Rejected? (And How to Prevent It)
This is the section that saves money. LEM rejections delay invoices, damage client relationships, and in some cases result in revenue that never gets collected because no one follows up properly.
The good news: Based on analysis of field work approvals processed through Aimsio’s platform, the most common rejection causes are preventable. Here’s what they are and how to stop them.
Missing or mismatched signatures. A LEM without the field supervisor’s signature, the client rep’s signature, or both is incomplete. Most clients won’t approve an unsigned ticket regardless of how accurate the data is. Picture a client rep who walked the site with your crew, saw the work done, and left without signing because it slipped. Three weeks later, getting that signature back is a phone call that may or may not happen. The fix is to make on-site sign-off a hard stop before anyone leaves the job.
Rates that don’t match the contract. If your bill rate for a journeyman operator is $95/hour and the LEM says $110, the client will reject it. This is one of the leading causes of billing disputes, and it almost always happens because a field crew member entered a rate from memory instead of pulling it from the agreed price book. Building rate lookups into the LEM process, rather than relying on people to remember them, is the structural fix.
Wrong or missing dates. A LEM submitted on Tuesday for work done Friday, entered with Wednesday’s date, creates a documentation problem that’s hard to resolve weeks later. It sounds like a basic error, and it is. But it happens constantly on paper-based operations. Date errors trigger requests for clarification that add days to the approval cycle every time.
Line items outside the approved scope. If a client’s work order didn’t include a specific equipment type and it shows up on the LEM, they’ll push back. Field crews sometimes add items without realizing the scope doesn’t cover them. Reviewing scope before submitting, not after rejection, is the habit worth building.
Missing PO or cost code references. Most large operators require a Purchase Order number and project cost codes on every LEM. Without them, the ticket gets kicked back. This is a process gap, not a people gap. If PO numbers aren’t captured at job setup, crews can’t include what they don’t have.
Illegible handwriting. This doesn’t apply to digital LEMs, but it’s still responsible for a share of rejections on paper-based operations. If the billing coordinator can’t read it, neither can the client. For the full list, see the top 10 reasons field tickets get rejected.
How Do You Get a LEM Approved Faster?
The approval process is where billing cycle time gets won or lost. A LEM that’s complete, accurate and in the client’s hands the same day can be approved within days. One that goes through three rounds of corrections and emails can take weeks.
A few things that consistently shorten the cycle:
Fill it out the same day. Work captured at the end of a shift is more accurate than work reconstructed two days later. Rates, hours, and quantities are fresh. The field supervisor is still available to answer questions.
Get on-site sign-off before anyone leaves. Client representative signatures obtained on-site are far easier to get than chasing someone down remotely after the fact.
Submit digitally. A digital LEM sent to the client through a portal removes the manual steps between completion and review. There’s no email chain, no PDF attachment that goes to the wrong person, and no week-long wait for someone to log into a portal they forgot the password to.
Know your client’s format. Major operators often have specific LEM templates or fields they require. Using their format from the start means fewer clarification requests. This is especially true for larger clients with formal procurement processes.
Paper LEMs vs. Digital LEMs: What’s the Practical Difference?
Most companies that still use paper LEMs aren’t doing it because they prefer paper. They’re doing it because switching feels complicated and the current process technically works. That’s a reasonable position, right up until it stops being true.
| Paper LEMs | Digital LEMs | |
|---|---|---|
| Where it’s filled out | Truck cab, site office, clipboard | Mobile app, on-site or offline |
| Rate accuracy | Crew enters manually, errors common | Pulled from price book automatically |
| Signature collection | Physical sign-off, easy to miss | Captured digitally, tracked |
| Submission speed | Hand-delivered or scanned and emailed | Submitted from the field, or on the next sync when crews are offline |
| Approval workflow | Manual follow-up required | Sent to the client for sign-off through the Client Portal |
| Audit trail | Paper file, easily lost or damaged | Permanent digital record |
| Billing cycle | Weeks | Days |
Paper works fine until something goes wrong. A lost ticket, a disputed rate, a missing signature from a client rep who is no longer reachable. Digital LEMs don’t fix bad process, but they remove a lot of the ways a good process fails.
How Does Aimsio Handle LEMs?
Aimsio is a field operations and billing platform built for industrial and commercial companies in North America, including oil and gas operators, energy contractors, construction firms and other heavy industrial service providers. It captures LEMs, field tickets and timesheets in the field and turns approved tickets into invoices.
In practice, here’s what that looks like. Field crews fill out LEMs on the Aimsio mobile app, including when there’s no cell service, and sync when they’re back in coverage. Bill rates come from the price book, so no one is entering numbers from memory. Signatures are captured digitally on-site, and submitted LEMs go to the client for sign-off through the Client Portal.
When a LEM is approved, it converts to an invoice in one click. There’s no data re-entry, no reconciliation against a separate system, and no week-long lag between the field and finance. Preferred Energy Services, an oil and gas contractor, used this workflow to reduce billing disputes and improve cash flow predictability in environments where connectivity is inconsistent and ticket volume is high.
Aimsio has processed more than 6.5 million field tickets and $13 billion in invoices. On the Aimsio platform, 91% of tickets are approved on first submission. That number is the direct result of eliminating the manual steps where errors enter.
If Your LEM Process Is Slowing Down Your Cash Flow, Here’s What to Do About It
Rejected tickets, delayed invoices, and billing disputes are symptoms. The underlying issue is usually a LEM process that was built for a lower volume of work than you’re running now. If your billing cycle is measured in weeks instead of days, and your office team spends meaningful time chasing signatures and correcting rate errors, the problem isn’t the people. It’s the process.
Aimsio’s digital LEM and Client Portal tools are built for exactly this situation: field teams who work in remote locations, clients who need a clean audit trail, and billing coordinators who should be closing invoices instead of reconciling paperwork.
See how Preferred Energy Services improved LEM approvals and cut billing lag in remote oilfield environments, then talk to someone on the Aimsio team about what that looks like for your operation.
See the Preferred Energy Case Study →
Frequently Asked Questions
What does LEM stand for?
LEM stands for Labour and Equipment Manifest, also spelled Labor and Equipment Manifest. Some companies expand it as Labor, Equipment and Materials. It records who worked, what equipment ran and what materials were used on a job, and it forms the basis of the client invoice.
What is a LEM in construction?
In construction, a LEM documents time-and-materials work: the crew hours, equipment and materials for work that isn't covered by a fixed-price contract, such as extra work or client-requested changes. The client signs it to approve the charges, and it becomes the backup for the invoice.
Is a LEM the same as a field ticket?
Not exactly. Field ticket is the general term for any record of work done in the field. A LEM is one type of field ticket, common in oil and gas, pipeline and construction time-and-materials work, that itemizes labor, equipment and often materials so the client can approve the charges. Every LEM is a field ticket, but not every field ticket is a LEM.
Who fills out a LEM?
Typically the field supervisor or foreman completes the LEM at the end of a shift or job. On larger sites, a company man or site coordinator may assist. The client representative usually signs off on-site to confirm the work and quantities before the crew leaves.
How long should a LEM take to get approved?
A complete, accurate LEM submitted digitally the same day the work is done can be approved within days. Paper or emailed LEMs that need follow-up commonly take weeks. The difference is almost entirely in how the LEM is submitted and sent to the client, not the approval itself.
What happens if a LEM is rejected?
The ticket goes back to whoever submitted it with the rejection reason. Common next steps: correct the error, resubmit, and wait for a second review cycle. Every rejection adds days to your billing cycle and risks revenue going uncollected if the issue isn't resolved. The best time to prevent a rejection is before the LEM leaves the field.